Project Title:
Project Planning for the F Area Deactivation Project

Client:
Westinghouse Savannah River Company

Location:
F Canyon Complex, Savannah River SiteAiken, South Carolina

Scope:
F Area Deactivation Support

Performance Period:
11/02 – 9/05

Project Planning for the F Area Deactivation Project

Polestar provided technical support to develop F Area Project Management Plan, revised facility end points, detailed cost estimates, safeguards and security optimization strategies and support on an Independent Baseline Review Team.

 

Polestar personnel assisted WSRC in developing project planning for the F Area Deactivation Project. Planning support by Polestar included:

  • Conducting (2) deactivation lessons learned work shops for key F Area staff
  • Development of the Project Management Plan
  • Development of the detailed cost estimate using the POWERtool estimating software developed by Polestar
  • Revision of the deactivation end points using the End Point software developed by Polestar Applied Technology, Inc.
  • Safeguard and Security Efficiency and Optimization Analysis
  • Support on Independent Baseline Review Team

In addition to planning support for the project, Polestar conducted a change capability assessment of the F Area organization and work process, provided leadership of breakthrough workshops to identify change opportunities, and subsequently led an organizational and work process redesign to position the F Area from an operational organization and work management structure to a Project organization with work processes streamlined for the deactivation project. This redesign effort is anticipated to yield significant cost and schedule improvement (as much as 40%) over the project life-cycle.

Polestar staff provided virtually continuous on-site support for this effort with a core team of staff members conducting weekly site visits. Polestar also provided two staff members to lead the redesign. This support was provided on a continuous basis on-site from the end of November 2002 through the end of February 2003, at which time the redesign was ready for implementation. Implementation support continues on an interim basis through the end of September 2003.